How much soil comes out of a basement dig? (Bank vs loose, with the math)

By the Give Me The Cost estimating team · Methods reviewed by a senior GTA estimator (25+ years in the field) · Updated July 2026
The short answer: take the hole's volume and add 25–40%. Excavated soil expands ('swells') when dug — clay by 30–40%, loam ~25%, sand 10–15%. You pay trucking and disposal on the swelled (loose) volume, not the hole. A typical full-basement dig produces 300–500 loose cubic yards — 25 to 40 tandem truckloads.

The three-step math

Step 1 — Bank volume (the hole): dig length × width × depth. A 50′ × 20′ footprint dug 7′-6″ deep = 7,500 cubic feet = 278 cubic yards in the ground ("bank" volume).

Step 2 — Apply the swell factor: clay till (most of Toronto) swells about 35% when excavated. 278 yd³ × 1.35 = ~375 loose cubic yards on trucks. That's the number your excavation quote is based on.

Step 3 — Truckloads: a tandem dump truck carries roughly 14 loose yd³. 375 ÷ 14 ≈ 27 loads. On a tight street with live loading (no stockpile room), that's the whole job's rhythm.

Soil typeSwell factor278 yd³ bank becomes…
Sand / gravel1.10–1.15~310 loose yd³
Loam / silt~1.25~350 loose yd³
Clay / clay till (GTA typical)1.30–1.40~375–390 loose yd³

The real swell factor comes from your geotechnical report — don't guess on a big dig.

Details estimators include (and DIYers miss)

Topsoil strip is its own line — the top 6 inches comes off first and is handled separately. Working space: add about 2 feet beyond the footing faces for formwork and waterproofing access (3 feet when the cut is deeper than 4 feet) — but zero where the face is shored at a property line. Exclusions: contaminated soil and dewatering are typically the owner's cost, priced only when discovered — ask how your quote treats them.

Why disposal is the budget killer

Excavation subs typically quote per loose cubic yard of disposal plus day rates for machine and labour. Since swell inflates every bank yard by a third, and Toronto disposal fees depend on soil classification, the dirt leaving the site usually costs more than the digging itself.

Run your own numbers in 30 seconds with our free excavation calculator.

Want your project's real numbers, not ranges?
Upload your drawings and get an actual material takeoff with an Ontario Building Code check — or start with the free calculators.
Get my takeoff →   Free calculators

Frequently asked questions

How many truckloads is a basement excavation?
A typical full-basement dig of 270–350 bank cubic yards becomes 350–470 loose cubic yards after swell — roughly 25–35 tandem truckloads at ~14 loose yd³ per load.

What is a swell factor?
How much soil expands when excavated from its compacted natural state. Clay swells 30–40%, loam about 25%, sand 10–15%. Disposal is billed on the swelled volume.

Why is my excavation quote per cubic yard higher than the hole size?
Because subs quote on loose (swelled) disposal volume plus machine/labour day rates — not on the neat geometric hole.

Do I need a geotechnical report?
For any new build or underpinned basement, yes — it sets the swell factor, bearing capacity, water table and frost depth. Lenders and engineers will ask for it anyway.